Construction conditions for water-based epoxy flooring:
1. Chisel and clean the cement mortar on the ground. If there are grease impurities on the ground, use a solvent to wipe it clean.
2. The original cement floor requires hardness, smoothness, and no sanding. If there are hollowing, peeling, sanding, cracks, etc. on the floor, they must be treated according to the requirements before construction can begin. If the original ground is a smooth surface such as terrazzo or floor tiles, it needs to be chiseled into a rough surface first.
3. As long as there is no water accumulation or obvious leakage, construction can be carried out. The relative humidity at the construction site should be below 85%, and the ambient temperature should be above 10 ℃.