Suggestions for cutting expansion joints in epoxy flooring
Answer: The principle is to cut every 5-7 meters to a width of 3 millimeters and a depth of 2 centimeters, and inject sealant (not within the scope of hardened epoxy floor construction)
The thickness of the concrete slab poured in two stages is about 5cm:
(1) The construction process is basically the same as item A.
(2) The concrete mix proportion should use fine aggregate concrete with smaller particle size (less than 1/2).
(3) In order to ensure the complete bonding between new and old concrete, the old concrete surface should be cleaned of all foreign objects, floating slag, and impurities, kept clean, coated with interface adhesive or roughened, or sprayed with pure cement slurry before pouring.